Question 47
During validation of a project solution, the business analyst discovers that a requirement has been altered.
Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.
Which correct action should the business analyst take?
Question 48
A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.
How can the business analyst determine the impact on existing requirements?
Question 49
Which of the following best describes the function of the requirements baseline?
Question 50
A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.
What is the most effective way to manage this situation?
Question 51
A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.
What should the business analyst do to ensure that the business need can be validated?