Question 27
A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.
What document should the business analyst use to determine the relationship of the requirement to the business need?
Question 28
The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and and with a lean budget. What should the team do to reduce the risk of rework?
Question 29
How can a SWOT analysis help when deciding between several possible options to address a business problem?
Question 30
The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?
Question 31
The project team is working on test scripts to test a solution. Which source can be used for building tests of end-to-end business processes across business functions and systems?