Question 671
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
Question 672
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
Question 673
You assigned staff members to activities, estimated work and scheduled your project. Then, you depicted the following resource histogram for your staff:
Exhibit:
What is the diagram telling you?
Question 674
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
Question 675
A key stakeholder of a project wants to include additional work before completion.
What should the project manager do?