Question 71
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
Question 72
During project execution, a project member informs the project manager that a project deliverable may not be completed on time due to a new customer requirement. What should the project manager do to ensure the project timeline is met?
Question 73
Activity A has a duration of three days and begins on the morning of Monday the 4th. The successor activity, B, has a finish-to-start relationship with A.
The finish-to-start relationship has three days of lag, and activity B has a duration of four days. Sunday is a non workday. Such data can help to determine______________
Question 74
A company made several changes recently, which resulted in a positive change in the company culture. A project manager was just assigned to report to a new project supervisor whose leadership style is about getting things done quickly regardless of employee and operational impacts. Some employees are complaining about this.
What should the project manager do?
Question 75
The following table shows the business value created and the development effort required to implement various features in a product
Which feature should the team prioritize first? Enter the feature name in the box below