Question 306
During a bridge construction project, a project manager discovers that one of the suppliers is the subject of a political issue. This could negatively impact the project.
What should the project manager do next?
Question 307
Keeping up with the growth was becoming a problem for a privately owned Chinese financial services company. Although it easily lured business from state-owned competitors, low skill levels and weak accounting systems threaten the company's cash flow. Moreover, poorly invested assets were delivering inadequate returns. Hence, you have been assigned over an existing project to upgrade the IT system to allow for an expansion. Specifically, the IT upgrade
will enable the company to serve more competitors, expand the product line, gain market share, and win more licenses. You've determined the following information so far: Activity X has an
early start of day3, early finish of day6, and a late finish of day10. Activity Y is being performed by resource that had been very difficult to obtain. The CPI of the project is 1.2
and the SPI is 1.3.
Midway through your project, your client has requested additional deliverables to your project. Fortunately, you have already determined that this functionality will only add one extra week to the critical path. To accommodate this request, you've determined that you could fasttrack
the schedule to recover one extra week. Which of the following should you perform NEXT?
Question 308
A complex project is closing and many project team members report negative experiences The project stakeholders from various areas of" the organization may never work together again As part of the project's requirements the project manager must provide lessons learned How should the project manager ensure this requirement is met?
Question 309
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
Question 310
A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.