Question 36
Which phrasebest describes a Product Owner?
Question 37
Currently, your Development Teams are organized to address a single layer only (for example, front end,
middle tier, back end, and interfaces). What are three things to consider when deciding to move away from
such component teams toward feature teams? (Choose three.)
Question 38
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
Question 39
Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).
Question 40
Which of the following are true about the length of the Sprint? (Choose two.)