Question 81
Project risk is defined as the cumulative effect of chances of _____ which will adversely affect project objectives.
Question 82
A risk was identified at the beginning of a project, and a response plan was established.
Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan.
What should the project manager do?
Question 83
If your project is under budget, your cost variance (CV) is:
Question 84
A project team Is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.
What should the project manager do?
Question 85
A new project has high uncertainty in the cost required for completion. What approach should the project manager use to determine the expected costs?
