Question 61
A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the
selected items "Done" by the end of the Sprint. Which three phrases best describe the purpose of a
definition of "Done"? (Choose three.)
Question 62
Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)
Question 63
The Development Team should have all the skills needed to: (Choose the best answer.)
Question 64
Which topics should be discussed in the Sprint Review?
Question 65
Which of the following best describes an increment of working software? (Choose the best answer.)