Question 56
During the Sprint Review, the Product Owner decides to release the current Increment to production. The stakeholders suggest temporarily delaying the next Sprint in order to respond more quickly to user feedback after the release. The Product Owner prefers to continue to the next Sprint and make progress towards the next release. Steven, the Scrum Master, begins facilitating the discussion.
What would be two acceptable outcomes of the discussion? (Choose two.)
Question 57
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
Question 58
At the Sprint Planning, the Development Team is not able to forecast the number of Product Backlog items it can do in the upcoming Sprint due to unclear requirements. The Product Owner, however, was able to clearly define the business objective he hopes to achieve in the Sprint.
Which of the following two actions would you support? (Choose two.)
Question 59
Technical Debt can lead to false assumptions about the current state of the system and the Increment reviewed at the end of the Sprint.
Question 60
Stakeholders are only allowed to meet with the Scrum Team at Sprint Review.