Question 36
During a program's definition phase, it is determined that the best approach for delivering the programs intended benefits is to supplement corporate resources with the procurement of specific products and services from external suppliers.
The program manager should use which of the following to determine and/or document the results of the program procurement planning activity?
Question 37
You have just finished a design calling for 15 telecommunications outlets. You received word that the owner has increased his requirements by 40%.
What size commercial DD (distribution device) is required to accommodate the increase?
Question 38
A 3 trade size conduit is sized at
Question 39
A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources.
Before initiating closeout and releasing the resources, what should the program manager do?
Question 40
66-style connecting blocks (certain designs) can support up to what category of transmission performance?