Question 116
While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:
* Approved Work Package Cost Estimates: US$9,500
* Contingency reserves: $500 %
* Management reserves: 10% of contingency reserves
* Percent complete of the project: 50%
* Planned percent of the project: 40%
* Actual costs of the project: US$4,500
What is accurate about the project status?
Question 117
Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?
Question 118
An output of the Create WBS process is:
Question 119
As head of the PMO, you will receive performance reports for all major projects. You decided to set a guideline for project managers as performance reporting should______________
Question 120
Which type of risk diagram is useful for showing time ordering of events?