Question 11
Which of the following would a Contract Administrator use if they are using a unilateral contract?
Question 12
An organization is considering a new program. The business analyst believes that the benefits to the organization would equate to $1,550,000 in five years. If the rate of return for this program is six percent what is the maximum amount the organization should invest in this program?
Question 13
A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?
Question 14
A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year. Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation, as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured.
What should the program manager do to address the risk?
Question 15
Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?