Question 426
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
Question 427
In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0,75 and the cost performance index (CPI) is 1,25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control.
How should the project manager report the project status to key stakeholders?
Question 428
A project is in the closure phase. The deliverables have been approved by the project sponsor. However, the team that will support the delivered product is complaining about a lack of documentation.
What should the project manager have done to prevent this scenario?
Question 429
An issue requires the execution of the project's contingency plan, which impacts the schedule. What should the project manager do?
Question 430
Crosswind Custom Homes is building a customer's dream house. However, rain has delayed the finish by two weeks. The Project Manager is evaluating options to make up the lost time. After discussing the various options with senior management, the Project Manager has decided to fast track the project. By doing so, the Project Manager could be adding what to the project?