A project manager is managing a new client. The project requires knowledge of upcoming technologies, but existing team member have no experience working with hue technologies. What should the project manager do to engage the team in work relating to these technologies?
Correct Answer: C
Question 437
A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?
Correct Answer: D
Question 438
After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features What should the project manager do to avoid this in the future?
Correct Answer: C
Question 439
A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project What should the project manager have the project team update to ensure proper communications to stakeholders?
Correct Answer: C
The stakeholder register is a project document that identifies and classifies the project stakeholders, their roles, interests, expectations, and influence levels. It is an output of the Identify Stakeholders process, which is the first process in the Project Stakeholder Management knowledge area. The stakeholder register should be updated whenever there are changes in the project environment or stakeholder information, such as a promotion, a change of role, or a change of contact details. Updating the stakeholder register will help the project manager and the project team to communicate effectively and appropriately with the stakeholders, and to manage their expectations and engagement levels throughout the project life cycle. The project management plan is a comprehensive document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates the subsidiary plans and baselines from the different knowledge areas, such as scope, schedule, cost, quality, resources, communications, risk, procurement, and stakeholder management. The project management plan is an output of the Develop Project Management Plan process, which is the second process in the Project Integration Management knowledge area. The project management plan should be updated only when there are changes in the project scope, objectives, deliverables, or approach, and when these changes are approved through the Perform Integrated Change Control process. Updating the project management plan for a stakeholder promotion is not necessary, unless it affects the project scope or other aspects of the project. The stakeholder engagement plan is a subsidiary plan of the project management plan that describes the strategies and actions to increase the support and minimize the resistance of the stakeholders throughout the project. It is an output of the Plan Stakeholder Engagement process, which is the second process in the Project Stakeholder Management knowledge area. The stakeholder engagement plan should be updated when there are changes in the stakeholder engagement levels, needs, or expectations, and when these changes are approved through the Perform Integrated Change Control process. Updating the stakeholder engagement plan for a stakeholder promotion may be required, depending on how it affects the stakeholder's interest, influence, or power over the project. The communications management plan is a subsidiary plan of the project management plan that describes the communication methods, formats, frequency, and responsibilities for the project. It is an output of the Plan Communications Management process, which is the first process in the Project Communications Management knowledge area. The communications management plan should be updated when there are changes in the communication requirements, preferences, or channels of the project stakeholders, and when these changes are approved through the Perform Integrated Change Control process. Updating the communications management plan for a stakeholder promotion may be necessary, depending on how it affects the stakeholder's communication needs or preferences. Therefore, the correct answer is C. Stakeholder register, as it is the most relevant and appropriate document to update for a stakeholder promotion. References: * PMBOK Guide, 6th edition, pages 513-515, 520-521, 538-539, 563-564, 717-718. * PMP Exam Content Outline, June 2019, pages 6-7, 10-11, 14-15, 18-19.
Question 440
A new project team consists of team members from different departments who have varying levels of experience and different areas of expertise. Which three approaches should the project manager take in order to facilitate knowledge sharing? (Choose 3)
Correct Answer: A,B,E
Facilitating knowledge sharing in a cross-functional and diverse team is essential for team integration and improved performance. Creating informal and structured opportunities like daily learning sessions, retrospectives for knowledge exchange, and shadowing enables team members to learn from one another and develop a shared understanding. According to the PMBOK Guide - Seventh Edition and the Agile Practice Guide, knowledge transfer is best facilitated through collaborative activities, peer learning, and continuous feedback loops. Option C focuses more on gap assignment than active knowledge sharing. Option D is valid in some cases but leans toward external intervention rather than internal team collaboration. References: PMBOK Guide - Seventh Edition, Team Performance Domain Agile Practice Guide, Section 5.3.2 - Team Learning and Knowledge Sharing -