Question 156
A program meeting was held virtually to discuss the program scope. Without face-to-face interactions, the program charter seemed ambiguous and program team members appear to be lacking motivation and are unsure of their roles. What should the program manager do to improve productivity?
Question 157
What quality control chart compares two or more variables over time to determine how closely the variables may be related to one another?
Question 158
Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?
Question 159
A program manager is assigned to a large cross-functional program that includes five different technologies and multiple workstreams.
Some potential stakeholders have conflicting program expectations.
What should the program manager do next?
Question 160
An infrastructure program has 20 projects. The first half of these projects incurred multiple change orders and failed to be completed on time. The program manager meets with the project managers to discuss lessons learned and to understand the challenges. During the meeting, the project managers complain that key risks and a lack of resources resulted in missing deadlines.
What should the program manager do to ensure that the remaining 10 component projects stay on track?