Question 91
A program manager for a construction program composed of several components is conducting a program status meeting with the program team. The project manager for the component projects reports the following status: Component A is running behind schedule, component B is running ahead of schedule, and component C is running well behind schedule due to a delay in vendor delivery. What should the program manager do to reflect the changes?
Question 92
You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time.
What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?
Question 93
After new private equity owners acquire an enterprise, they want to improve its value by reducing costs. A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed. A strategic component project presents significant risk to organizational objectives due to its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility. Implementation of this component project may now begin, but is already one month behind schedule. The program manager now perceives significantly more risk to the larger program due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?
Question 94
You are the program manager for your organization that utilizes vendors from several different organizations. A vendor has submitted an invoice for the work they have completed in your program. You have reviewed the work results and agree with the vendor that their contractual obligation is complete.
What should you do next in regard to the vendor's invoice?
Question 95
Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned into operations. They claim that their department did not approve this service, and is now unprepared and untrained to support the transformation.
What should the program manager have done first to prevent this?